Dear all,
I would like to call a process B through a process A with a call activity, but it doesn’t work.
My call activity has been set up with the following parameters:
- Id = ID
- Name = NAME
- Called Element Type = Key
- Called Element = process B key
I have deployed both process A and B on the same application, and when I try to complete the user task before my call activity it gives me the following error message: “task xyz cannot be completed”
Do you have any input on what could be the source of this error ?
Best,